Contents
|
Progress on building a house on Lakeside Court.
- March 11, 2006
- After two and one half years we remain very happy! The website has been completely redone to reflect what we know and to be more user friendly than the original site. Please visit the revised site.
- June 20, 2004
- We have been in the house for a year and are very pleased with the result. Still have minor punch list items but the major ones have all been resolved. With one year of heating data and 18 months of solar data, we have a much better idea of the efficiency of the house. We are using roughly 1/2 of the amount of gas as the old house and producing about 65% of our electrical load (Averaged over a year. During 5 months we are net producers of power, but then our demands go up as the weather turns colder and our production goes down as well.) See the new page on actual electrical and heating production. Note that the 18 month data are much more accurate than my optimistic estimates of August 13. Landscaping that went in last summer is doing very well. The bamboo in the garden is now between 6-8 feet tall and still growing.
- September 7, 2003
- Slowly, oh so slowly, working our way through the punch list of things that need to be finished and fixed. Did some corrections to the wiring for the battery banks and replaced a cable connecting the two Trace Inverters. This seems to have allowed the second inverter to start working properly. Further tests of the 2nd inverter shows that it is working fine now. Thanks to tech support at Trace for their help.
- August 13, 2003
- Since we moved in (June 20th) we have been averaging 22.5 KWH of PV production and 19KWH of consumption for a net sale back to the grid of about 3 KWH/day. We tend to sell about 11 KWH/day and buy (at night) about 8. We still have some construction work going on (e.g., painters and some carpentry) that probably is driving our consumption up slightly. Although we have bought 439 KWH from the grid since June 20th, we have sold back 610 for a net addition to the grid of 171 KWH over 54 days. We have not tuned the inverters for optimal production and have had some problems with one of them failing when under battery operation. Now that we have more than 6 months of data, it is useful to observe monthly averages of the total daily output, output per slate/field, and to compare consumption to production.
- August 12, 2003
- Hard to keep updating the page when everything is so wonderful. Some recent exterior shots (including one interior of the bamboo railings for the stair case) show that most landscaping is done and most external construction is done. Punch list continues (and continues).
- June 20, 2003
- Moved in!
- March 2, 2003
- Bamboo floors are being installed, and they look great (photos to follow).
Atlantis Solar slates have now been producing power for 1 month. We have produced 400 Kwh for February with daily output averaging 12.8Kwh and varying from 4.5 to 25 Kwh. Power consumption is running about 3 times as high as predicted (presumably because we are running 2 dehumidifiers 24 hours a day to dry out the trim and flooring, running table saws, compressors for nail guns, etc.) and has been averaging 54 Kwh/day. Therefore, by producing 12.8 kwh/day we are producing only about 23% of our total power consumption.
- March 1, 2003
- Have done empirical calculations on energy use for January and February. Even with construction going on and the resulting infiltration of open doors, unfinished vents, etc. the house is very efficient.
- February, 2003
- waiting for bamboo to be chosen (problems with various suppliers), prepping for radiant heating, problems with gypcrete installation, miscellaneous frustrations.
- January 28, 2003
- Two way electric meter installed so that we can now integrate the solar slates with the grid.
- December 27
- Altantis Solar slates have been installed on garage, roof is finished! Note the use of Non-Power slates on garage makes for a cleaner line.
- December 10
- Altantis Solar Slates have been installed on Belvedere and 2nd Floor, roof is finished except for garage and front porch
- October 28
- Insulation starts going in, shingles added to the Belvedere, solar panel framework is installed, electrical equipment for PV arrives and is mounted.
- October 6
- Interiors of the Belvedere, wrap around views from the Belvedere.
- October 5
- The house is coming together and looking more and more like a real house. The exterior window trim is almost finished, 1st floor and 2nd floor plumbing are finished, electrical piping is almost finished.
- September 24-28th:
- Exterior trim, interior framing, plumbing
- September 6-11
- windows installed, temporary stairs
- September 4
- Windows arrive! Plumbing and HVAC are underway, continued discussions about kitchen design
- August 28
- Underroof is finished, Waterproofing is installed, chimney is raised
- August 27
- views in and from the belvedere
- August 10
- walls of the belvedere are finished
- August 4
- starting the belvedere ridge
- July 12
- joists for second floor
- July 5
- interior walls almost finished
- July 3
- starting on the interior walls
- June 30
- making good progress on walls
- June 29
- Working on the walls
- June 28
- Walls are starting to go up
- June 25
- Finished first floor deck
- June 20
- working on the first floor deck
- June 18
- Electrical box and grounding, (not connected to power)
- June 17
- Sewer and water connections, further cross supports for floor joists
- June 16
- Floor joists are almost finished
- June 4
- Steel beams are in
- May 28
- Waterproofing added to outside of walls, drain tiles installed, back fill the overdig
- May 21
- Foundation walls are poured (slightly too short!)
- May 13
- Footings finished.
- May 7
- Frames for footings are put in
- April 30
- Demolition is finished, digging is finished, waiting for the survey before pouring concrete.
- April 25
- Demolition is finished, one more survey and digging starts.
- April 23
- House demolition finally starts!
- April 17
- dumpster can not make it. Power shovel continues to wait.
- March 25
- Gas company still has not disconnected the gas.
- March 21
- Electrical off. Demolition scheduled for March 25.
- March 17
- Removal of cabinets, lighting fixture, door knobs.
- March 10
- Yet another demolition party, once again demolition expected within a week.
- Feb 17
- Demolition party open house for neighbors, demolition expected within a week.
- Sept-December, 2001
- Working on the plans and model for the house.
|